- Brazil's state oil company Petrobras has started up a new 180,000 barrel-per-day rig, meeting its 2007 goal for new capacity, if not production, after months of delays.
- It is the second rig with that production capacity to start working on Roncador in the past two weeks and the third platform to go on-stream since Nov 16
- The rigs are slowly ramping up production and should reach capacity by the end of the first half of next year, when more platforms are expected to be launched.
- All the rigs have suffered delays due to problems with suppliers in an overheated market as well as the complexity of the projects, but still, Petrobras added 560,000 bpd capacity this year as planned, proving that Brazil is a key area of new world crude output growth.
- Because of the long delays with bringing on-stream the new rigs and slow ramp-up at others, Petrobras output should rise just between 1 percent this year from last year's average of 1.78 million bpd, below the initial growth target of about 10 percent.
- Domestic oil output by Petrobras fell 2.3 percent in October to 1.73 million bpd from September in its fourth straight monthly drop and was a steep 5 percent below year-ago levels, but the company says November presented an ascending production curve again.